June 2015
Historic Zoning Commission
Meeting Information

Below is the monthly archive for the June 2015 Historic Zoning Commission meeting, including the agenda, meeting minutes, and the recording of the meeting.

Agenda Minutes

Actions from the June 2015, meeting

6-A-15-HZ Approved with conditions

Level l repairs:
1. Repair of deteriorated brick foundation walls after removal of concrete porch. Use historic mortar recipe (9:2:1)
2. Repair damaged siding and replace rotten or missing siding with wood siding to match. Paint entire exterior and add aluminum gutters.

Level II changes:

1. Remove concrete porch floor and fdn. and replace with new wood porch floor (framing and tongue & groove decking) on new CMU foundation piers with painted parge coat (see phase 1). Piers and floor framing to be built to accommodate construction of porch roof (see Phase 2 dwgs).
2. Porch posts: two 8x8 chamfered wooden posts and two pilasters against the front façade.
3.Porch railing: install 2x2 square balusters with a molded top rail with the spacing between balusters being 3 inches.
4.Porch skirt area: install wooden lattice installed so that the lattice strips run parallel and perpendicular to the porch floor, rather than on the diagonal.
5.Porch roof: full-façade hipped with asphalt shingle covering.
6. Wrap non-original square back porch columns with wood fascia (see Phase 1 dwgs) so that they are no larger than 6x6, and add treated wood trellis for climbing plants (see exterior views).
7. Replace non-original double-hung windows with wood double-hung . Add appropriate window casing (see submitted drawings) (Phase 1dwgs).
8. Replace front door with wood half-lite door with 2 vertical or horizontal wood panels below (see Phase 1 dwgs).


6-B-15-HZ Approved

6-C-15-HZ Approved

6-D-15-HZ Approved as Modified

Construct 8' x12' frame side-gabled shed on masonry piers. Cladding to be engineered composite panels with 2-inch battens applied over the vertical reveals to appear as board and batten sheathing. Entry door with board and batten to be centered on side. Shed to be situated with a 5-foot setback from the north side lot line and 48 feet from the rear lot line. Side gabled roof to have a 8/12 roof pitch and to be sheathed in asphalt shingles. Lattice work is to fill in between the foundation piers. Roof is also approved as a hipped roof. Vertical reveals on composite sheathing panels to be approximately 12-inches on-center.


7-F-15-HZ Approved