January 2013
Historic Zoning Commission
Meeting Information

Below is the monthly archive for the January 2013 Historic Zoning Commission meeting, including the agenda, meeting minutes, and the recording of the meeting.

Agenda Minutes

Actions from the January 2013, meeting

1-A-13-HZ Approved as Modified

Rebuild chimney stack on the west sides of house to match original chimney stack existing prior to demolition on 12-3-12. Flashing technique must assure waterproofing of chimney stack structure. Southeast chimney to have brick corbelling at top. Reconstructed with masonry construction or as per submitted drawing using a framed substrate.


1-B-13-HZ Approved

1-C-13-HZ Approved

1-D-13-HZ Approved

1-E-13-HZ Approved

12-A-12-HZ Approved as Modified

APPROVE front porch balustrade w/conditions:1) balusters to be installed to fit between top/bottom rail, 2) top/bottom rail to be parallel to porch floor, 3) step rails to have balusters to match balustrade, & 4) step rail to die into a wooden newel post w/cap. Balustrade and step rails and balustrade to be painted.