Use On Review

9-M-01-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for a college in the PC/TO zoning district, subject to 11 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Obtaining a BZA variance to reduce the minimum parking stall areas from 200 square feet to 180 square feet for this site and noting it on revised plans.
2. Meeting the requirements of the Development Corporation of Knox County. (See attached letter dated Aug. 31, 2001)
3. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA).
4. Meeting all requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. Meeting all applicable requirements of the Knox County Health Department.
7. Installing all landscaping, as shown on the development plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
8. Moving the northwest curbcut to align with the curbcut on the opposite side of Centerpoint Blvd, without losing any parking spaces.
9. Obtaining approval of signage by TTCDA and MPC prior to any signs being placed on the site.
10. Submitting a lighting plan showing location of all proposed lighting and indicating no spillover of light or glare off-site.
11. Submitting a revised site plan to MPC for certification, reflecting the above conditions, prior to issuance of any building permits for this project.

With the conditions noted above, this request meets the requirements for approval in the PC zone, and the other criteria for approval of a use on review.

Applicant Request

+

Property Information

+
Location
Northeast side of Centerpoint Blvd., northwest side of Lovell Rd.

Commission District 6


Size
4.29 acres

Sector
Northwest County

Land Use Designation? Commercial


Currently on the Property
Vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for a college in the PC/TO zoning district, subject to 11 conditions:
1. Obtaining a BZA variance to reduce the minimum parking stall areas from 200 square feet to 180 square feet for this site and noting it on revised plans.
2. Meeting the requirements of the Development Corporation of Knox County. (See attached letter dated Aug. 31, 2001)
3. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA).
4. Meeting all requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. Meeting all applicable requirements of the Knox County Health Department.
7. Installing all landscaping, as shown on the development plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
8. Moving the northwest curbcut to align with the curbcut on the opposite side of Centerpoint Blvd, without losing any parking spaces.
9. Obtaining approval of signage by TTCDA and MPC prior to any signs being placed on the site.
10. Submitting a lighting plan showing location of all proposed lighting and indicating no spillover of light or glare off-site.
11. Submitting a revised site plan to MPC for certification, reflecting the above conditions, prior to issuance of any building permits for this project.

With the conditions noted above, this request meets the requirements for approval in the PC zone, and the other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a college in the PC/TO zoning district, subject to 11 conditions:
Details of Action
1. Obtaining a BZA variance to reduce the minimum parking stall areas from 200 square feet to 180 square feet for this site and noting it on revised plans.
2. Meeting the requirements of the Development Corporation of Knox County. (See attached letter dated Aug. 31, 2001)
3. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA).
4. Meeting all requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. Meeting all applicable requirements of the Knox County Health Department.
7. Installing all landscaping, as shown on the development plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
8. Moving the northwest curbcut to align with the curbcut on the opposite side of Centerpoint Blvd, without losing any parking spaces.
9. Obtaining approval of signage by TTCDA and MPC prior to any signs being placed on the site.
10. Submitting a lighting plan showing location of all proposed lighting and indicating no spillover of light or glare off-site.
11. Submitting a revised site plan to MPC for certification, reflecting the above conditions, prior to issuance of any building permits for this project.

With the conditions noted above, this request meets the requirements for approval in the PC zone, and the other criteria for approval of a use on review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - October 13, 2001 - has passed.

The Process
Applicant

Barber & McMurry Inc.


Case History