Details of Action
−
+
1) Installing the proposed landscaping as shown on the landscape plan within six months of the tower becoming operational, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
2) Maintaining the natural tree buffer around the tower site to help reduce the visual impact of the tower.
3) Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
4) At the time of the request for a building permit, posting a bond or other approved financial surety that would ensure the removal of the tower if it is abandoned.
5) Meeting all applicable requirements of the Knox County Zoning Ordinance.
6) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7) A revised site plan, reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.
Property Information
−
+
LocationSouthwest of Choto Rd., southeast of S. Northshore Dr., and north of Early Rd.
Commission District 5
Size31.37 acres
Sector
Currently on the Property
Vacant land
Growth PlanRural Area
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for a 195 foot telecommunications tower subject to 7 conditions.
1) Installing the proposed landscaping as shown on the landscape plan within six months of the tower becoming operational, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
2) Maintaining the natural tree buffer around the tower site to help reduce the visual impact of the tower.
3) Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
4) At the time of the request for a building permit, posting a bond or other approved financial surety that would ensure the removal of the tower if it is abandoned.
5) Meeting all applicable requirements of the Knox County Zoning Ordinance.
6) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7) A revised site plan, reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.
Disposition Summary
APPROVE the development plan for a 195 foot telecommunications tower subject to 7 conditions.
Details of Action
1) Installing the proposed landscaping as shown on the landscape plan within six months of the tower becoming operational, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
2) Maintaining the natural tree buffer around the tower site to help reduce the visual impact of the tower.
3) Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
4) At the time of the request for a building permit, posting a bond or other approved financial surety that would ensure the removal of the tower if it is abandoned.
5) Meeting all applicable requirements of the Knox County Zoning Ordinance.
6) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7) A revised site plan, reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.