Use On Review

9-J-13-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan and list of permitted uses for the reuse of the existing church buildings, subject to 4 conditions


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
205 Bridgewater Rd

Southwest side of Bridgewater Rd., southeast side of Comstock Rd.

Council District 2
Census Tract 46.03


Size
6.75 acres

Sector
Northwest County

Land Use Designation? GC/C pending


Currently on the Property
Church/meeting space/sports facility

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE the development plan and list of permitted uses for the reuse of the existing church buildings, subject to 4 conditions
1. Use of the facility shall be restricted to the uses identified on PC-1 Proposed Uses list (dated July 31, 2013) provided by the applicant, with the exclusion of the daycare use. Since the daycare use has specific requirements that cannot be met by the existing facilities, a separate use on review approval is required.
2. Meeting all applicable requirements of the Knoxville Department of Engineering.
3. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
4. Any proposed signage is subject to approval by Planning Commission staff and Knoxville's Sign Enforcement Inspector.

With the conditions noted above, this request meets the requirements for approval in the PC-1 (Retail and Office Park) zoning district, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan and list of permitted uses for the reuse of the existing church buildings, subject to 4 conditions

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - September 27, 2013 - has passed.

The Process
Applicant

Harb-White Properties, LLC


Case History