APPROVE the request for an expansion to the church parking lot and a building expansion for a storage area of approximately 580 square feet as shown on the development plan subject to 5 conditions.


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance
2. Installation of the sidewalk extension out to Lovell Rd. as designated on the development plan meeting all applicable requirements of the Americans with Disabilities Act ( ADA) and the Knox County Department of Engineering and Public Works.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Obtaining a driveway connection permit from the Tennessee Department of Transportation for the modifications to the entrance driveway.
5. Issuance of a Certificate of Appropriateness for the proposed development by the Tennessee Technology Corridor Development Authority (TTCDA) and compliance with any conditions of that certificate.

With the noted conditions, this plan meets the requirements for approval in the BP (Business and Technology) zoning district and the other criteria for approval of a Use on Review.

Applicant Request

+

Property Information

+
Location
1432 Lovell Rd

Southeast side of Lovell Rd., southwest side of Pellissippi Parkway.

Commission District 6
Census Tract 59.03


Size
10.96 acres

Sector
Northwest County

Land Use Designation? Office


Currently on the Property
Church

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the request for an expansion to the church parking lot and a building expansion for a storage area of approximately 580 square feet as shown on the development plan subject to 5 conditions.
1. Meeting all applicable requirements of the Knox County Zoning Ordinance
2. Installation of the sidewalk extension out to Lovell Rd. as designated on the development plan meeting all applicable requirements of the Americans with Disabilities Act ( ADA) and the Knox County Department of Engineering and Public Works.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Obtaining a driveway connection permit from the Tennessee Department of Transportation for the modifications to the entrance driveway.
5. Issuance of a Certificate of Appropriateness for the proposed development by the Tennessee Technology Corridor Development Authority (TTCDA) and compliance with any conditions of that certificate.

With the noted conditions, this plan meets the requirements for approval in the BP (Business and Technology) zoning district and the other criteria for approval of a Use on Review.
Disposition Summary
APPROVE the request for an expansion to the church parking lot and a building expansion for a storage area of approximately 580 square feet as shown on the development plan subject to 5 conditions.
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance
2. Installation of the sidewalk extension out to Lovell Rd. as designated on the development plan meeting all applicable requirements of the Americans with Disabilities Act ( ADA) and the Knox County Department of Engineering and Public Works.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Obtaining a driveway connection permit from the Tennessee Department of Transportation for the modifications to the entrance driveway.
5. Issuance of a Certificate of Appropriateness for the proposed development by the Tennessee Technology Corridor Development Authority (TTCDA) and compliance with any conditions of that certificate.

With the noted conditions, this plan meets the requirements for approval in the BP (Business and Technology) zoning district and the other criteria for approval of a Use on Review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - October 14, 2017 - has passed.