Row Closure

9-C-12-SC

Recommended for approval
by the Planning Commission

approve the closure subject to conditions


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Construction does not meet City of Knoxville requirements

Close Street From
southwest terminus
To
northeast terminus
Reason for Closure
Construction does not meet City of Knoxville requirements
Objections

No objections from any departments or utilities have been received by staff as of 9/6/12.


Property Information

+
Location
0 Peppercorn Ln

Council District 3
Census Tract 48


Sector
Northwest City

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
RECOMMEND that City Council APPROVE the closure of Peppercorn Ln., subject to any required easements and subject to the following condition;.
1. The four conditions included in the attached letter from City of Knoxville Engineering (dated August 28, 2012) must be addressed to the satisfaction of that department.

With the above condition included, staff has received no objections to this closure. The applicant owns all the private property adjacent to this right-of-way.
Disposition Summary
approve the closure subject to conditions

What's next?

+
After the Planning Commission
This Row Closure case in the City was recommended for approval. The appeal deadline - September 28, 2012 has passed.
Applicant

Jefferson Federal Bank


Case History