Property Information
−
+
LocationNorth end of Gatekeeper Way, northwest of Ball Camp Pike.
Commission District 6
Census Tract 46.06
Size5.11 acres
Sector
Currently on the Property
Vacant land
Growth PlanPlanned Growth Area
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerWest Knox Utility District
TelephoneAT&T
WaterWest Knox Utility District
Case Notes
−
+
Staff Recommendation
APPROVE the Concept Plan subject to 4 conditions:
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Obtaining the variance from the Knox County Board of Zoning Appeals to eliminate the creek buffer zones as outlined in the Knox County Stormwater Ordinance. If the variance is not granted, the final plat will have to identify the required creek buffers and adjust the lots/lot lines in order to comply with the buffer requirements.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Meeting all applicable requirements of the Knox County Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval of a concept plan in the PR zoning district.
Disposition Summary
APPROVE the Concept Plan subject to 4 conditions: