Use On Review

7-E-10-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for a 14 pump gas fueling station, subject to 6 conditions:


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
9147 Middlebrook Pike

Northeast side of Middlebrook Pike, north end of N. Cedar Bluff Rd.

Commission District 3
Census Tract 46.06


Size
1.19 acres

Sector
Northwest County

Land Use Designation? Commercial


Currently on the Property
Vacant building

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for a 14 pump gas fueling station, subject to 6 conditions:
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Installation of the intersection improvements on the shopping center parcel, as identified on the approved development plan, prior to the issuance of an occupancy permit for the fueling center.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Meeting all applicable requirements and obtaining any required permits for the proposed signage from the Knox County Sign Administrator.
5. Installing all landscaping, as shown on the development plan, within six months of the issuance of occupancy permits for this project.
6. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted, this plan meets the requirements for approval in the PC zoning district and all criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a 14 pump gas fueling station, subject to 6 conditions:

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - August 7, 2010 - has passed.

The Process
Applicant

The Kroger Company


Case History