Use On Review

6-C-01-UR

Approved as modified
by the Planning Commission

APPROVE the request to expand the existing mining operation as shown on the development plan and limit the new area to be mined to the 24.72 acres permitted by the State of Tennessee, subject to 10 conditions


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all requirements of the Knox County Health Dept.
2. Approval of the development plan and mining permit by the Knox County Commission.
3. Provision of a copy of the site restoration plan approved by the State of Tenn. prior to commencing any excavation on the expanded site.
4. Restoring the property per the State approved plan if operations are discontinued for a period of one year.
5. Provision of the air quality permit which establishes the standards the mine operator's must comply with.
6. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation dealing with the mining operation and water quality permits.




General Shale Products Corp.
6-C-01-UR
Page 2


7. Meeting all requirements of the Knox County Dept. of Engineering and Public Works.
8. Obtaining approval of another Use on Review if the mining area is to be expanded beyond the State approved 24.72 acres or if it takes more than fifteen years to mine the permitted area as called for in the Plan of Operation.
9. Meeting all applicable requirements including Sections 4.10 and 4.50 of the Knox County Zoning Ordinance.
10. (Added by MPC) Applicant will begin reclamation of the eastern portion of the existing mine site except for the stockpile area which is actively utilized within six (6) months of beginning operation of this mine site.

Applicant Request

+

Property Information

+
Location
North side of Millertown Pike, east of Harris Rd.

Commission District 8


Size
107 acres

Sector
Northeast County

Currently on the Property
Vacant

Growth Plan
Rural Area

Case Notes

+
Staff Recommendation
APPROVE the request to expand the existing mining operation as shown on the development plan and limit the new area to be mined to the 24.72 acres permitted by the State of Tennessee, subject to 9 conditions
1. Meeting all requirements of the Knox County Health Dept.
2. Approval of the development plan and mining permit by the Knox County Commission.
3. Provision of a copy of the site restoration plan approved by the State of Tenn. prior to commencing any excavation on the expanded site.
4. Restoring the property per the State approved plan if operations are discontinued for a period of one year.
5. Provision of the air quality permit which establishes the standards the mine operator's must comply with.
6. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation dealing with the mining operation and water quality permits.
7. Meeting all requirements of the Knox County Dept. of Engineering and Public Works.





General Shale Products Corp.
6-C-01-UR
Page 2


8. Obtaining approval of another Use on Review if the mining area is to be expanded beyond the State approved 24.72 acres or if it takes more than fifteen years to mine the permitted area as called for in the Plan of Operation.
9. Meeting all applicable requirements including Sections 4.10 and 4.50 of the Knox County Zoning Ordinance.
Disposition Summary
APPROVE the request to expand the existing mining operation as shown on the development plan and limit the new area to be mined to the 24.72 acres permitted by the State of Tennessee, subject to 10 conditions
Details of Action
1. Meeting all requirements of the Knox County Health Dept.
2. Approval of the development plan and mining permit by the Knox County Commission.
3. Provision of a copy of the site restoration plan approved by the State of Tenn. prior to commencing any excavation on the expanded site.
4. Restoring the property per the State approved plan if operations are discontinued for a period of one year.
5. Provision of the air quality permit which establishes the standards the mine operator's must comply with.
6. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation dealing with the mining operation and water quality permits.




General Shale Products Corp.
6-C-01-UR
Page 2


7. Meeting all requirements of the Knox County Dept. of Engineering and Public Works.
8. Obtaining approval of another Use on Review if the mining area is to be expanded beyond the State approved 24.72 acres or if it takes more than fifteen years to mine the permitted area as called for in the Plan of Operation.
9. Meeting all applicable requirements including Sections 4.10 and 4.50 of the Knox County Zoning Ordinance.
10. (Added by MPC) Applicant will begin reclamation of the eastern portion of the existing mine site except for the stockpile area which is actively utilized within six (6) months of beginning operation of this mine site.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.
After the Planning Commission
Because of its location in the County, appeals will be heard by County Commission.
County Commission
June 25, 2001
Appeal by: August 11, 2001
July 23, 2001
Appeal by: August 13, 2001

The appeal deadline - August 11, 2001 - has passed.

The Process
Applicant

General Shale Products Corp.


Case History