Rezoning

One Year Plan Amendment

4-E-17-RZ

Recommended for denial
by the Planning Commission

DENY the rezoning to O-1 (Office, Medical & Related Services), consistent with the denial recommendations for the associated plan amendments.


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
3503 Tazewell Pike

Northwest side Tazewell Pike, southwest of Fieldcrest Ln.

Council District 4
Census Tract 42


Size
11,682 square feet

Sector
North City

Land Use Designation? LDR


Currently on the Property
Residence

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
DENY the rezoning to O-1 (Office, Medical & Related Services), consistent with the denial recommendations for the associated plan amendments.
The existing transitional zoning pattern to the southwest is appropriate and has established a good stopping point for non-residential uses heading north along Tazewell Pike. O-1 zoning will allow uses that require more off-street parking than low density residential. The paved parking area currently in front of the house could provide that parking, but a significant portion of the paved area is in public right-of-way (see attached aerial photo). Along the north and east sides of the house, where additional parking could be located, the topography would make it difficult and very disruptive to the adjacent neighborhood to construct parking there. Variances on parking would likely be needed if the property were rezoned to O-1.
Disposition Summary
DENY the rezoning to O-1 (Office, Medical & Related Services), consistent with the denial recommendations for the associated plan amendments.

What's next?

+
As a denied Rezoning case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.
After the Planning Commission
  • Appeal to Because of its location in the City, appeals will be heard by Knoxville City Council
  • Appeal by The appeal deadline has passed
The Process