Subdivision

Concept Plan

3-SE-07-C

Recommended for approval
by the Planning Commission

APPROVE the Concept Plan subject to 8 conditions


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+
Subdivision
I-40 / I-75 Business Park Revised
Lots
18 (Split)
Residential?
No

Variances

None


Property Information

+
Location
North side of El Camino Ln., west of Everett Rd.

Commission District 6


Size
46.55 acres

Sector
Northwest County

Currently on the Property
Vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the Concept Plan subject to 8 conditions
1. Meeting all applicable requirements of the Knox County Zoning Ordinance
2. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works
3. Provision of the left turn lane from Watt Rd. on to El Camino Ln. as called for in the traffic impact study . Plans for the turn lane and the timing of its construction must be approved by the Knox County Dept. of Engineering and Public Works and/or TDOT. All construction work done in the public right-of-way must be coordinated through and supervised by the Knox County Dept. of Engineering and Public Works and/or TDOT
4. Posting a bond with the Knox County Dept. of Engineering and Public Works for up to five years to cover the cost of the traffic signal purchase and installation at the intersection of Watt Rd. and El Camino Ln. at the time that it is warranted as called for in the traffic impact study
5. Roads constructed within the project will be built to County's standard for a "commercial/ industrial" street as required by the Knox County Dept. of Engineering and Public Works
6. Meeting all requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation
7. All cut slopes within the development not exceeding a 2 to 1 slope. A landscaping plan must be submitted that addresses the revegetation of the cut slopes.
8. A final plat based on this concept plan will not be accepted for review by MPC until certification of design plan has been submitted to MPC staff
Disposition Summary
APPROVE the Concept Plan subject to 8 conditions

What's next?

+
After the Planning Commission
Because of its location in the County, appeals will be heard by Knox County Chancery Court.
Appeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

I-40 / I-75 Business Park Revised

Watt Road Partners, LLC


Case History