Use On Review

3-L-02-UR

Approved
by the Planning Commission

APPROVE the development plan for an educational facility expansion of up to 19,000 square feet, subject to 6 conditions.


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Installing landscaping as shown on the landscape plan within six months of the issuance of occupancy permit for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Compliance with all conditions of the previous Use-on-Review (1-L-00-UR) approved for this site.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.

With the conditions noted, this plan meets the requirements for approval of a Use-on-Review.

Applicant Request

+

Property Information

+
Location
8833 Middlebrook Pike

North side of Middlebrook Pike, east side of Pheasants Glen Dr.

Commission District 5


Size
10.95 acres

Sector
Northwest County

Currently on the Property
Church

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for an educational facility expansion of up to 19,000 square feet, subject to 6 conditions.
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Installing landscaping as shown on the landscape plan within six months of the issuance of occupancy permit for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Compliance with all conditions of the previous Use-on-Review (1-L-00-UR) approved for this site.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.

With the conditions noted, this plan meets the requirements for approval of a Use-on-Review.
Disposition Summary
APPROVE the development plan for an educational facility expansion of up to 19,000 square feet, subject to 6 conditions.
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Installing landscaping as shown on the landscape plan within six months of the issuance of occupancy permit for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Compliance with all conditions of the previous Use-on-Review (1-L-00-UR) approved for this site.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.

With the conditions noted, this plan meets the requirements for approval of a Use-on-Review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - May 11, 2002 - has passed.

The Process
Applicant

Damon A. Falconnier for West Park Baptist Church


Case History