Use On Review

3-H-06-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for up to 60 detached single family dwellings on individual lots subject to 3 conditions


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Approval of the rezoning request before Knox County Commission to increase the maximum density for the PR (Planned Residential) zoning district to 2.5 du/ac (2-M-06-RZ).
2. Meeting all applicable requirements of the approved concept subdivision plan.
3. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted, this plan meets the requirements for approval of the concept plan in the PR zone and the other criteria for approval of a use-on-review

Applicant Request

+

Property Information

+
Location
10929 Snyder Rd

Northwest side of Snyder Rd. at the north end of Clover Fields Ln.

Commission District 5


Size
23.87 acres

Sector
Northwest County

Land Use Designation? LDR & SLPA


Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for up to 60 detached single family dwellings on individual lots subject to 3 conditions
1. Approval of the rezoning request before Knox County Commission to increase the maximum density for the PR (Planned Residential) zoning district to 2.5 du/ac (2-M-06-RZ).
2. Meeting all applicable requirements of the approved concept subdivision plan.
3. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted, this plan meets the requirements for approval of the concept plan in the PR zone and the other criteria for approval of a use-on-review
Disposition Summary
APPROVE the development plan for up to 60 detached single family dwellings on individual lots subject to 3 conditions
Details of Action
1. Approval of the rezoning request before Knox County Commission to increase the maximum density for the PR (Planned Residential) zoning district to 2.5 du/ac (2-M-06-RZ).
2. Meeting all applicable requirements of the approved concept subdivision plan.
3. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted, this plan meets the requirements for approval of the concept plan in the PR zone and the other criteria for approval of a use-on-review

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - April 8, 2006 - has passed.

The Process
Applicant

Fred Long Construction Concepts


Case History