Details of Action
−
+
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Meeting all applicable requirements of the Knoxville Department of Engineering.
3. Installing all landscaping, as shown on the development plan, within six months of the issuance of occupancy permits for this project.
4. Meeting all applicable requirements and obtaining any required permits for the proposed signage from the Knoxville Sign Administrator.
5. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval in the SC-1 zoning district and all criteria for approval of a use on review.
Property Information
−
+
Location4440 Western Ave
Southwest side of Western Ave., southeast of Hinton Dr.
Council District 3
Census Tract 38
Size3.88 acres
SectorLand Use Designation? Commercial
Currently on the Property
Supermarket and shopping center
Growth PlanUrban Growth Area (Inside City Limits)
- Utilities
SewerKnoxville Utilities Board
WaterKnoxville Utilities Board
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for a 6 pump / 12 bay gas fueling station, subject to 5 conditions:
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Meeting all applicable requirements of the Knoxville Department of Engineering.
3. Installing all landscaping, as shown on the development plan, within six months of the issuance of occupancy permits for this project.
4. Meeting all applicable requirements and obtaining any required permits for the proposed signage from the Knoxville Sign Administrator.
5. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval in the SC-1 zoning district and all criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a 6 pump / 12 bay gas fueling station, subject to 5 conditions:
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Meeting all applicable requirements of the Knoxville Department of Engineering.
3. Installing all landscaping, as shown on the development plan, within six months of the issuance of occupancy permits for this project.
4. Meeting all applicable requirements and obtaining any required permits for the proposed signage from the Knoxville Sign Administrator.
5. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval in the SC-1 zoning district and all criteria for approval of a use on review.