Staff Recommendation
APPROVE. Proposed work is consistent with adopted design guidelines and with Commission review of October 17, 2002.
APPROVE. Proposed work is consistent with adopted design guidelines and with Commission review of October 17, 2002.
Repair brick as necessary; install cornice at top of building and above storefront; install aluminum cladding on existing window framing.
Haynes Building. Two story brick building with segmental arched second story windows, corbelled cornice, altered storefront. One-third of a three bay building which includes #33 and #35. Two over two double hung windows. Storefront rehabilitated to correct proportions with wooden bulkhead, large store windows and transom Recessed multipane front door. Red brick surface on wall with buff brick outlining segmental window arches.
Commission is asked to RATIFY Certificate No. 12202(#31)MKT.