APPROVE the development plan for a 34,272 square foot office building in the BP/TO zone, subject to 6 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. Obtaining approval of a Certificate of Appropriateness, with any required waivers, and meeting all applicable requirements of the Tennessee Technology Corridor Development Authority (TTCDA). The Certificate is scheduled to be considered by TTCDA on December 6, 2004.
6. Approval of variance from the Knox County Board of Zoning Appeals as follows: variance to allow parking within the south, east and west 50 feet front setback (from edge of right of way) areas along Data Lane and Corridor Park Boulevard. A BZA variance to reduce the parking stall size from 200 to 171 square feet may also be required.

Applicant Request

+

Property Information

+
Location
Southwest side Data Ln., southwest of Corridor Park Blvd.

Commission District 6
Census Tract 59.01


Size
3.22 acres

Sector
Northwest County

Land Use Designation? Technology Park


Currently on the Property
Vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for a 34,272 square foot office building in the BP/TO zone, subject to 6 conditions:
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. Obtaining approval of a Certificate of Appropriateness, with any required waivers, and meeting all applicable requirements of the Tennessee Technology Corridor Development Authority (TTCDA). The Certificate is scheduled to be considered by TTCDA on December 6, 2004.
6. Approval of variance from the Knox County Board of Zoning Appeals as follows: variance to allow parking within the south, east and west 50 feet front setback (from edge of right of way) areas along Data Lane and Corridor Park Boulevard. A BZA variance to reduce the parking stall size from 200 to 171 square feet may also be required.

With the conditions noted above, this request meets the requirements for approval in the BP/TO zone, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a 34,272 square foot office building in the BP/TO zone, subject to 6 conditions:
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. Obtaining approval of a Certificate of Appropriateness, with any required waivers, and meeting all applicable requirements of the Tennessee Technology Corridor Development Authority (TTCDA). The Certificate is scheduled to be considered by TTCDA on December 6, 2004.
6. Approval of variance from the Knox County Board of Zoning Appeals as follows: variance to allow parking within the south, east and west 50 feet front setback (from edge of right of way) areas along Data Lane and Corridor Park Boulevard. A BZA variance to reduce the parking stall size from 200 to 171 square feet may also be required.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - January 8, 2005 - has passed.