Use On Review

12-E-16-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for the expansion of the existing Montessori School subject to 8 conditions.


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Connecting to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Meeting all applicable requirements of the Knoxville Department of Engineering.
3. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Transportation for the revised access driveways for the site.
4. Obtaining approval and recording a plat for the combination of the two parcels or a plat that establishes the permanent access easements that are needed for the one-way traffic flow across the two parcels.
5. Meeting all applicable requirements of the Knoxville Fire Marshal's Office.
6. Installation of all landscaping as shown on the landscape plan within six months of the issuance of occupancy permit for this project.
7. Meeting all applicable requirements of the Knoxville Urban Forester.
8. Meeting all applicable requirements of the Knoxville Zoning Ordinance.

With the conditions noted above, this request meets all requirements for approval in the R-1 zoning district, as well as other criteria for approval of a use on review.

Applicant Request

+

Property Information

+
Location
4301 Kingston Pike

North side of Kingston Pike, north side of the intersection of Towanda Trail and Kingston Pike

Council District 2
Census Tract 37


Size
0.90 acres

Sector
West City

Land Use Designation? LDR and HP


Currently on the Property
Residence and school

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE the development plan for the expansion of the existing Montessori School subject to 8 conditions.
1. Connecting to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Meeting all applicable requirements of the Knoxville Department of Engineering.
3. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Transportation for the revised access driveways for the site.
4. Obtaining approval and recording a plat for the combination of the two parcels or a plat that establishes the permanent access easements that are needed for the one-way traffic flow across the two parcels.
5. Meeting all applicable requirements of the Knoxville Fire Marshal's Office.
6. Installation of all landscaping as shown on the landscape plan within six months of the issuance of occupancy permit for this project.
7. Meeting all applicable requirements of the Knoxville Urban Forester.
8. Meeting all applicable requirements of the Knoxville Zoning Ordinance.

With the conditions noted above, this request meets all requirements for approval in the R-1 zoning district, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for the expansion of the existing Montessori School subject to 8 conditions.
Details of Action
1. Connecting to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Meeting all applicable requirements of the Knoxville Department of Engineering.
3. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Transportation for the revised access driveways for the site.
4. Obtaining approval and recording a plat for the combination of the two parcels or a plat that establishes the permanent access easements that are needed for the one-way traffic flow across the two parcels.
5. Meeting all applicable requirements of the Knoxville Fire Marshal's Office.
6. Installation of all landscaping as shown on the landscape plan within six months of the issuance of occupancy permit for this project.
7. Meeting all applicable requirements of the Knoxville Urban Forester.
8. Meeting all applicable requirements of the Knoxville Zoning Ordinance.

With the conditions noted above, this request meets all requirements for approval in the R-1 zoning district, as well as other criteria for approval of a use on review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.
After the Planning Commission
Because of its location in the City, appeals will be heard by Knoxville City Council.
Knoxville City Council
February 28, 2017
Appeal by: January 27, 2017

The appeal deadline - January 27, 2017 - has passed.

The Process
Applicant

Knoxville Montessori Association


Case History