Use On Review

12-A-11-UR

Approved as modified
by the Planning Commission

APPROVE the development plan for up to 96 residential units for the second phase of an apartment complex subject to the following 7 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
3. Provision of street names which are consistent with the Uniform Street Naming and Addressing system Ordinance (Ord. 91-1-102).
4. Installing all landscaping, as shown on the landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. The proposed new gate location is subject to final design approval by the Knox County Fire Marshal and the Knox County Department of Engineering and Public Works
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
(Original condition #7 was deleted by MPC. While the site specific parcel did not comply with the Sector Plan's medium density limitation, the
MPC action to delete this condition was based on the fact that the overal apartment development did comply with the medium density limitation.)
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted above, this request meets all requirements of the OB/TO zoning districts, as well as other criteria for approval of a use on review.

Applicant Request

+

Property Information

+
Location
0 Greenland Way

Northeast side of Greenland Way, south of Hardin Valley Rd.

Commission District 6
Census Tract 59.01


Size
7.30 acres

Sector
Northwest County

Land Use Designation? C/MDR/MU-SD


Currently on the Property
Vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for up to 96 residential units for the second phase of an apartment complex subject to the following 8 conditions:
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
3. Provision of street names which are consistent with the Uniform Street Naming and Addressing system Ordinance (Ord. 91-1-102).
4. Installing all landscaping, as shown on the landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. The proposed new gate location is subject to final design approval by the Knox County Fire Marshal and the Knox County Department of Engineering and Public Works
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Prior to obtaining any occupancy permits for the fourth building in this second phase of the development, recording a final plat that combines Lots 7 and 8 and a portion of the Joint Permanent Easement (JPE) (Greenland Way) of The Village at Hardin Valley subdivision into a single lot that brings the overall density to less than 12 du/ac.
8. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted above, this request meets all requirements of the OB/TO zoning districts, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for up to 96 residential units for the second phase of an apartment complex subject to the following 7 conditions:
Details of Action
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
3. Provision of street names which are consistent with the Uniform Street Naming and Addressing system Ordinance (Ord. 91-1-102).
4. Installing all landscaping, as shown on the landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. The proposed new gate location is subject to final design approval by the Knox County Fire Marshal and the Knox County Department of Engineering and Public Works
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
(Original condition #7 was deleted by MPC. While the site specific parcel did not comply with the Sector Plan's medium density limitation, the
MPC action to delete this condition was based on the fact that the overal apartment development did comply with the medium density limitation.)
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted above, this request meets all requirements of the OB/TO zoning districts, as well as other criteria for approval of a use on review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - January 7, 2012 - has passed.

The Process
Applicant

The Enclave Phase 2