Property Information
−
+
LocationSoutheast side of Carter Mill Dr., northeast of Carter Ridge Dr.
Commission District 8
Census Tract 53
Size14.90 acres
Sector
Currently on the Property
Developing subdivision and vacant land
Growth PlanPlanned Growth Area
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerKnoxville Utilities Board
TelephoneBell South
WaterKnoxville Utilities Board
Case Notes
−
+
Staff Recommendation
APPROVE the Concept Plan subject to 9 conditions
1. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
2. Construction of a sidewalk along the entire frontage of this site to the adjoining Paschal Carter Memorial Park and within the development as shown on the revised concept plan. All sidewalks are to be a minimum of 4' wide with a 2' planting strip between the back of the curb and the sidewalk. All sidewalk construction must comply with the provisions of the Americans with Disabilities Act.
3. Place a note on the final plat that all lots will have access from the internal street system only.
4. Prior to final plat certification, establish a homeowners association for the purpose of assessing fees for the maintenance of the proposed drainage structures, open space and other commonly held assets.
5. Connection to sanitary sewer and meeting any other applicable requirement of the Knox County Health Dept.
6. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (Ord. 91-1-102).
7. Reservation of sanitary sewer capacity through KUB. Prior to final plat approval provide MPC staff with a letter from KUB noting that sewer capacity is available
8. Place a note on the final plat that the side yard setback is 10' on each side of a dwelling when the road grade in front of the dwelling is 10% or greater
9. A final plat based on this concept plan will not be accepted for review by MPC until certification of design plan has been submitted to MPC staff
Disposition Summary
APPROVE the Concept Plan subject to 9 conditions