Property Information
−
+
LocationSoutheast side of Raccoon Valley Dr., west side of I-75
Commission District 7
Size19 acres
Sector
Currently on the Property
Vacant land
Growth PlanPlanned Growth Area
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerHallsdale-Powell Utility District
TelephoneMetro Group Bell South Telephone
WaterHallsdale-Powell Utility District
Case Notes
−
+
Staff Recommendation
APPROVE variances 1 & 2 because the site's topography and existing site conditions restrict compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard.
APPROVE the Concept Plan subject to 9 conditions:
1. Approval of the rezoning request for Tax Parcel 026 098 by Knox County Commission (11-E-04-RZ).
2. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
3. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
4. Conducting compaction testing in all existing and proposed fill areas associated with street construction and lot development per the requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
6. Obtaining a street connection permit from the Tennessee Department of Transportation.
7. Place a note on the final plat that all lots, except Lot 1, shall have access only to the internal street system.
8. Meeting all applicable requirements of the Knox County Zoning Ordinance.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
With the conditions noted, this plan meets the requirements for approval of a Concept Plan.
Disposition Summary
APPROVE variances 1 & 2 because the site's topography and existing site conditions restrict compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard.
APPROVE the Concept Plan subject to 9 conditions: