Use On Review

11-Q-01-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for up to 215 detached single family dwellings on individual lots subject to 5 conditions


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all requirements of the approved concept subdivision plan
2. Constructing the sidewalks shown on the development plan to a minimum width of 5'
3. Provision of a detailed landscaping plan to buffer and separate the double frontage lots adjoining S. Northshore Dr. ( Lots 1-8 Section 3 and Lots 31-41 Section 1).
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.
5. Installing all landscaping along S. Northshore Dr. within six months of the issuance of the first occupancy permit for any of the lots along S. Northshore Dr. or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.

With the conditions noted, this plan meets the requirements for approval in the PR zone and the other criteria for approval of a use on review.

Applicant Request

+

Property Information

+
Location
South side S. Northshore Dr., east of Harvey Rd.

Commission District 5


Size
81 acres

Sector
Southwest County

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for up to 215 detached single family dwellings on individual lots subject to 5 conditions
1. Meeting all requirements of the approved concept subdivision plan
2. Constructing the sidewalks shown on the development plan to a minimum width of 5'
3. Provision of a detailed landscaping plan to buffer and separate the double frontage lots adjoining S. Northshore Dr. ( Lots 1-8 Section 3 and Lots 31-41 Section 1).
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.
5. Installing all landscaping along S. Northshore Dr. within six months of the issuance of the first occupancy permit for any of the lots along S. Northshore Dr. or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.

With the conditions noted, this plan meets the requirements for approval in the PR zone and the other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for up to 215 detached single family dwellings on individual lots subject to 5 conditions
Details of Action
1. Meeting all requirements of the approved concept subdivision plan
2. Constructing the sidewalks shown on the development plan to a minimum width of 5'
3. Provision of a detailed landscaping plan to buffer and separate the double frontage lots adjoining S. Northshore Dr. ( Lots 1-8 Section 3 and Lots 31-41 Section 1).
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.
5. Installing all landscaping along S. Northshore Dr. within six months of the issuance of the first occupancy permit for any of the lots along S. Northshore Dr. or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.

With the conditions noted, this plan meets the requirements for approval in the PR zone and the other criteria for approval of a use on review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - December 8, 2001 - has passed.

The Process
Applicant

Martha Leeville, GP


Case History