Use On Review

11-O-07-UR

Recommended for approval
by the Planning Commission

APPROVE the request for a 150' monopole telecommunications tower in the A zoning district, subject to the following 5 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering & Public Works.
3. Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
4. Installing a 6' high security fence around the tower and equipment area prior to the tower becoming operational.
5. At the time of the request for a building permit, posting a bond or other approved financial surety that would ensure the removal of the tower if it is abandoned.

With the conditions noted above, this request meets all criteria for a use-on-review in the A zoning district.

Applicant Request

+

Property Information

+
Location
6323 Ridgeview Ln

North side of Ridgeview Rd., southeast of Tazewell Pike

Commission District 8
Census Tract 64


Size
2.75 acres

Sector
Northeast County

Land Use Designation? AG/RR


Currently on the Property
Residence and vacant land

Growth Plan
Rural Area

Case Notes

+
Staff Recommendation
APPROVE the request for a 150' monopole telecommunications tower in the A zoning district, subject to the following 5 conditions:
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering & Public Works.
3. Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
4. Installing a 6' high security fence around the tower and equipment area prior to the tower becoming operational.
5. At the time of the request for a building permit, posting a bond or other approved financial surety that would ensure the removal of the tower if it is abandoned.

With the conditions noted above, this request meets all criteria for a use-on-review in the A zoning district.
Disposition Summary
APPROVE the request for a 150' monopole telecommunications tower in the A zoning district, subject to the following 5 conditions:
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering & Public Works.
3. Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
4. Installing a 6' high security fence around the tower and equipment area prior to the tower becoming operational.
5. At the time of the request for a building permit, posting a bond or other approved financial surety that would ensure the removal of the tower if it is abandoned.

With the conditions noted above, this request meets all criteria for a use-on-review in the A zoning district.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - December 8, 2007 - has passed.

The Process
Applicant

U.S. Cellular Corporation


Case History