APPROVE the development plan for the expansion of a self-service storage facility in the CA zone, subject to 6 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. All outdoor lighting shall be shielded to direct light and glare away from all adjoining property.
2. Installing and maintaining all landscaping as shown on the development plan within six months of issuance of occupancy permit for the project.
3. Completing all drainage improvements for the phase one development as required by the Knox County Department of Engineering and Public Works.
4. Meeting all other applicable requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.

With the conditions noted above, this request meets all requirements for approval in the CA zone, as well as other criteria for approval of a use on review.

Applicant Request

+

Property Information

+
Location
7144 Clinton Hwy

Northeast side of Clinton Hwy., northeast of Larkspur Ln.

Commission District 6
Census Tract 61.01


Size
2.72 acres

Sector
North County

Land Use Designation? C & STPA


Currently on the Property
Vacant land and a portion of a parking lot for a vacant commercial center

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for the expansion of a self-service storage facility in the CA zone, subject to 6 conditions:
1. All outdoor lighting shall be shielded to direct light and glare away from all adjoining property.
2. Installing and maintaining all landscaping as shown on the development plan within six months of issuance of occupancy permit for the project.
3. Completing all drainage improvements for the phase one development as required by the Knox County Department of Engineering and Public Works.
4. Meeting all other applicable requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.

With the conditions noted above, this request meets all requirements for approval in the CA zone, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for the expansion of a self-service storage facility in the CA zone, subject to 6 conditions:
Details of Action
1. All outdoor lighting shall be shielded to direct light and glare away from all adjoining property.
2. Installing and maintaining all landscaping as shown on the development plan within six months of issuance of occupancy permit for the project.
3. Completing all drainage improvements for the phase one development as required by the Knox County Department of Engineering and Public Works.
4. Meeting all other applicable requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.

With the conditions noted above, this request meets all requirements for approval in the CA zone, as well as other criteria for approval of a use on review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - December 9, 2006 - has passed.