Rezoning

Northwest County Sector Plan Amendment

11-D-13-RZ

Recommended for approval
by the Planning Commission

RECOMMEND the Knox County Commission approve EC (Employment Center) zoning, subject to one condition.


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
South side Garrison Dr., south of Boomerang Ln.

Commission District 6
Census Tract 59.02


Size
69.86 acres

Sector
Northwest County

Land Use Designation? LDR & HP


Currently on the Property
Hay farming

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
RECOMMEND that County Commission APPROVE EC (Employment Center) zoning, subject to one condition.
1. All required road improvements, including but not limited to the completion of the Karns Valley connector to the west, resulting from the use on review approval of a development plan by MPC, must be completed to the satisfaction of MPC and Knox County Engineering staffs prior to the issuance of any occupancy permits for the project.

With the above condition, EC zoning is appropriate for the subject property. Staff recognizes the need for road improvements to accommodate the proposed business park. EC zoning requires use on review approval of a development plan by MPC, prior to development, which will provide the opportunity for public comment prior to development. A traffic study will be required to be submitted and reviewed as part of the required use on review process.
Disposition Summary
RECOMMEND the Knox County Commission approve EC (Employment Center) zoning, subject to one condition.

What's next?

+
After the Planning Commission
This Rezoning case in the County was recommended for approval. The appeal deadline - December 14, 2013 has passed.
Applicant

The Development Corporation of Knox County


Case History