Details of Action
−
+
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all requirements of the approved Use-on-Review development plan.
4. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Property Information
−
+
LocationSouth side of Brookshire Wy., south of Gleason Dr.
Commission District 5
Size2.99 acres
Sector
Currently on the Property
Vacant
Growth PlanPlanned Growth Area
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerFirst Knox Utility District
TelephoneMetro Group Bell South Telephone
WaterFirst Knox Utility District
Case Notes
−
+
Staff Recommendation
APPROVE variance 1 because the site's topography restricts compliance with the Subdivision Regulations, DENY variance 2 because the variance can be easily eliminated
APPROVE the concept plan subject to 4 conditions
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all requirements of the approved Use-on-Review development plan.
4. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Disposition Summary
APPROVE variance 1 because the site's topography restricts compliance with the Subdivision Regulations, DENY variance 2 because the variance can be easily eliminated
APPROVE the concept plan subject to 4 conditions
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all requirements of the approved Use-on-Review development plan.
4. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.