APPROVE the request for a fueling station as shown on the site plan subject to 4 conditions


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
2. Installing all internal traffic control measures as shown on the site plan prior to issuance of an occupancy permit for the fueling center
3. Meeting all applicable requirements of the City of Knoxville Dept. of Engineering
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff for certification prior to issuance of a building permit

Applicant Request

+

Property Information

+
Location
5753 Western Ave

North side of Western Avenue, west of Palmetto Road

Council District 3
Census Tract 47


Size
4.05 acres

Sector
Northwest City

Land Use Designation? C (Sector Plan), GC (One Year Plan)


Currently on the Property
Shopping center

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE the request for a fueling station as shown on the site plan subject to 4 conditions
1. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
2. Installing all internal traffic control measures as shown on the site plan prior to issuance of an occupancy permit for the fueling center
3. Meeting all applicable requirements of the City of Knoxville Dept. of Engineering
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff for certification prior to issuance of a building permit
Disposition Summary
APPROVE the request for a fueling station as shown on the site plan subject to 4 conditions
Details of Action
1. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Dept.
2. Installing all internal traffic control measures as shown on the site plan prior to issuance of an occupancy permit for the fueling center
3. Meeting all applicable requirements of the City of Knoxville Dept. of Engineering
4. A revised site plan reflecting the conditions of approval must be submitted to MPC staff for certification prior to issuance of a building permit

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - October 29, 2010 - has passed.