APPROVE variances 1-3 because the site's topography and shape restrict compliance with the Subdivision Regulations and the proposed variances will not create a traffic hazard.

APPROVE the Concept Plan subject to 12 conditions.


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+
Subdivision
The Moody Property
Lots
30 (Split)
Proposed Density
2.4 du/ac
Residential?
Yes - SF

Variances

1) Reduce the required tangent length of a broken back curve from 150' to 72.01' at STA 1+53.01 on Road "C".
2) Reduce the required tangent length of a reverse curve from 50' to 44.72' at STA 4+08.65 on Road "A".
3) Reduce the required depth of a double frontage lot from 150' to 125' along the shortest lot line for Lot 2.


Property Information

+
Location
0 Broome Rd

Southeast side of Broome Rd., south of Middlebrook Pike

Council District 2
Census Tract 45


Size
12.42 acres

Sector
Northwest City

Currently on the Property
Vacant land

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE variances 1-3 because the site's topography and shape restrict compliance with the Subdivision Regulations and the proposed variances will not create a traffic hazard.

APPROVE the Concept Plan subject to 12 conditions.

1. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Department and Knoxville Utilities Board.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knoxville (Ord. O-280-90).
3. Meeting all applicable requirements of the City of Knoxville Department of Engineering.
4. Placing a note on the final plat that all lots will have access to the internal street system only.
5. Prior to recording the final plat, establish a homeowners association for the purpose of assessing fees for the maintenance of the stormwater drainage facilities and all other commonly held assets.
6. Obtaining all necessary offsite utility easements per the requirements of the Knoxville Utilities Board.
7. Obtaining all necessary offsite stormwater drainage easements per the requirement of the City of Knoxville Department of Engineering.
8. Widening Broome Road to a minimum 20' pavement width from the Road "A" intersection to the location where the adjacent development to the northeast will end their road widening, and as approved by the City of Knoxville Department of Engineering.
9. Installation of sidewalks as identified on the Concept Plan. Sidewalks shall meet all applicable requirements of the Americans with Disabilities Act (ADA) and the City of Knoxville Department of Engineering. A bond shall be provided to the City of Knoxville Department of Engineering by the developer in an amount sufficient to guarantee the installation of the sidewalks. The sidewalk along Broome Rd. shall tie into the sidewalk being installed on the adjacent property to the northeast.
10. Submitting a sight distance certification letter from the applicants engineer for review and approval by the City of Knoxville Department of Engineering.
11. Installing multiple retention ponds in the approximate locations as shown on the Concept Plan. Additional retention ponds of similar or smaller size may be approved by Planning Commission staff and the City of Knoxville Department of Engineering if the proposal meets the intent of this approval to utilize multiple small retention ponds.
12. A final plat based on this Concept Plan will not be accepted for review by the Planning Commission until certification of design plan has been submitted to Planning Commission staff.
Disposition Summary
APPROVE variances 1-3 because the site's topography and shape restrict compliance with the Subdivision Regulations and the proposed variances will not create a traffic hazard.

APPROVE the Concept Plan subject to 12 conditions.

What's next?

+
After the Planning Commission
Because of its location in the City, appeals will be heard by Knox County Chancery Court.
Appeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

The Moody Property

JRG Development, LLC